Assignment name
Reconstruction converter gas cleaning piping systems in Steel & Iron company TŽ a.s. Třinec, Czech Republic
Name of the client
Třinecké železárny, a.s., Třinec
Short description
Detail design of overall reconstruction of LP and HP circulation piping systems related to the convertor systems including all relevant civil, electric and I&C systems.
Services provided by company
FE prepared and issued related documentation in Basic and Detail engineering phase of project and following framework of disciplines has been coordinated:
- Process engineering
- Mechanical engineering
- Civil Engineering
- I&C and Electrical systems The Basic Design (BD) elaborated by FE set up and developed the main scope of services and the interfaces between particular disciplines and battery limitsin terms of specific requirements of client for operation and maintenance. The Basic Design summarized all necessary technical information as the basis for execution of further Detail Design (DD) of the plant and covered following scope of works:
- Basic process data and heat balance calculations by means of available documents and existing operation practise
- Basic design and load data
- Process flow diagrams
- 3D-Model
- Basic arrangement and layout drawings
- Basic technical specification
- Suspension and Support concept
- I&C and electrical part concept
- Typical look-up diagrams The Detail Design (DD) included review and confirmation of BD results of all engineering and design services from the basic design (BD) phase and comprised as bellow :
- Final heat balance diagrams for various operation and transient operation cases
- 3D Model
- P&I diagrams
- Detail arrangement drawings of components (tanks, heat exchangers, headers etc.
- Detail layout drawing of plant ( platforms and sections)
- Dimensional check drawings
- Isometric drawings of pipelines
- Data sheets ( Vesels, Heat exchangers, Control Valves etc. )
- Static stress calculations
- Final technical specification ( valve list, List of lines, List of main equipments, List of hangers and supports ...
- Pipe stress analyses
- Bill of material
- Purchase specification
- Demolition and erection procedures
- I&C and electrical part documents (List of electrical consumers, List of measuring points) The Technical Advisory (TA) for the Clint includes technical support in tendering phase, Bid review and evaluation for manufacturing and delivery.
Country, location within country
Czech Republic, Třinec
Date beginning/completion
9.2013 - 8.2017
Technology
Type of service
TA
Staff involved in the project
ADAM Dominik
ARENDAS Vladimir
KATAY Tibor
MALIK Drahomir
SOJCAK Dusan
VALACH Branislav