Short description
Preliminary technical-economical evaluation of feasibility study of Coal Fired Power Plant Bana Cary - Alternative IVb (Coal fired Power Plant with CFB boiler and average unit load 100 MWe with anticipated operation period 8000 working hours)
Services provided by company
Technical and economical evaluation of feasibility study
- Checking and correction unit balance features as additive consumption, additional cooling water necessity, thermal efficiency of the boiler, etc
- Evaluation of technical solutions as main technological, electrical, I&C equipment design, civil design, etc.
- Economical evaluation
- Financial analysis and calculation of main economical indicators
- Technical – economical evaluation of considered options
- Time schedule revision proposal
- Final recommendation
Technical data
Coal fired Power Plant with CFB boiler and average unit load 100 MWe with anticipated operation period 8000 working hours
Country, location within country
Slovakia, Western Slovakia
Date beginning/completion
7.2008 - 10.2008
Technology
Coal PP
Type of service
FS
Staff involved in the project
ADAM Dominik
KOTRUS Marian
MALIK Drahomir